Abstract
This paper used PCTRAN that MST (Micro-Simulation Technology) design to analyzed Taiwan Power Company Lungmen Nnuclear Power Plants transient tests at Start-Up High/Mid Test Plateau.the goal of this paper is to simulate real test process against the results from the GE analyses for Lungmen Plant startup transient tests (STAR,Startup Test Prediction -Transient Test Prediction Revision 1 Draft B October 2009). The tests are (1)Loss of Feedwater Heater Event;(2)1feedwater pump trip event;(3)1 reactor internal pump trip event;(4) 3 reactor internal pump trip event. Lungmen Plant is not finished all pre-operation tests. Many setpoints have not been performed. The study referenced GE STAR and Lungmen Plant Final Safety Analysis Report (FSTR) to discuss simulate results.Setpoint can be confirmed after Lungmen Plant Start-Up test, that benchmark PCTRAN-ABWR model to upgrad accuracy.