A study of the flexible job shop scheduling problem with parallel machines and reentrant process
期刊文章   同儕審查

A study of the flexible job shop scheduling problem with parallel machines and reentrant process

J.C. Chen, K.H. Chen, J.J. WuC.W. Chen
International Journal of Advanced Manufacturing Technology, 卷.39(3-4), 頁碼.344-354
10/2008

摘要

Makespan On-time delivery Parallel machine Reentrant Control and Systems Engineering Software Mechanical Engineering Computer Science Applications Industrial and Manufacturing Engineering
This paper develops a scheduling algorithm for the job shop scheduling problem with parallel machines and reentrant process. This algorithm includes two major modules: the machine selection module (MSM) and the operation scheduling module (OSM). An order has several jobs and each job has several operations in a hierarchical structure. The MSM helps an operation to select one of the parallel machines to process it. The OSM is then used to schedule the sequences and the timing of all operations assigned to each machine. A real-life weapons production factory is used as a case study to evaluate the performance of the proposed algorithm. Due to the high penalty of delays in military orders, the on-time delivery rate is the most important performance measure and then makespan is the next most important measure. Well-known performance measures in the scheduling literature, such as maximum lateness and average tardiness, are also evaluated. The simulation results demonstrate that the MSM and OSM using the combination of earliest due date (EDD), the operations' lowest level code (LLC) of the bill of materials (BOM), and the longest processing time (LPT) outperforms the other scheduling methods. © 2007 Springer-Verlag London Limited.

相關連結

指標

1 檢視次數

詳細資料

Logo image