Minimizing makespan subject to minimum total absolute deviation of completion time on identical parallel machines
期刊文章

Minimizing makespan subject to minimum total absolute deviation of completion time on identical parallel machines

Ling-Huey Su, Fuh-Der ChouJames C. Chen
Engineering Optimization, 卷.44(10), 頁碼.1187-1195
10/2012

摘要

hierarchical criteria makespan parallel-machine scheduling total absolute deviation of job completion time Control and Optimization Industrial and Manufacturing Engineering Applied Mathematics Computer Science Applications Management Science and Operations Research
This study addresses the identical parallel machine scheduling problem with the objective of minimizing makespan subject to minimum total absolute deviation of job completion time (TADC). An optimization algorithm is first proposed to solve TADC on an identical parallel machine and an iterative procedure based on a polynomial binary integer programming model is then proposed to minimize makespan. Computational experiments show that the proposed algorithm is efficient. The worst case performance, which refers to the largest average execution for each scenario of the experiments, is 229.10seconds for the problem with n=200, m=30 and p j from a uniform [1, 100]. © 2012 Copyright Taylor and Francis Group, LLC.

相關連結

指標

1 檢視次數

詳細資料

Logo image